North Campus
project
Located in Fairlawn, Ohio this project consisted of 22,801 SF of
new addition and 18,000 SF of renovation. The 600 seat
Multi-Purpose Worship Center with state of the art sound and
production equipment could also serve as a recreational area
with retractable basketball hoops and removable volleyball nets.
The addition also housed a Serving Room, Green Room, Play Area
and Classrooms. One very unique feature is a slide from the main
level to the children’s area in the lower level. The main part
of the renovation was the conversion of the existing worship
area into a coffee house style gathering area that still retains
the ability to be used for small services. In testament to
Summit’s abilities, the project was completed in 10 months while
the facility was in full operation and Service’s were held every
week. |
 |

|
|
|