Greenon K-12 Facilities Project update 5.8.20
Enon, Ohio
The progress continues at Greenon Local School District’s new K-12 School. The 200,000 sf Facilities Project is marching forward with the majority of work now being done under roof.…
Read MoreEarly Childhood Center at Urban Community School update 5.5.20
Cleveland, Ohio
The progress continues at the Early Childhood Education Center on the campus of Urban Community School. As May begins, the roof membrane is complete, the exterior framing and…
Read MoreCharles Schwab in Westlake update 4.23.20
Westlake, Ohio
The interior buildout at Charles Schwab in Westlake is now in full swing with complete mep rough-ins, first coat of paint scheduled for next week, and drywall nearing completion…
Read MoreSafety during COVID-19
Akron, Ohio
Summit Construction has continued operations during the state of Ohio's ongoing battle with COVID-19 as an essential business. To create and maintain the safest work environment…
Read MoreLancaster General Sherman Junior High update 4.13.20
Lancaster, Ohio
Lancaster City School District's 106,000 sf General Sherman Junior High School is forging ahead to completion.
Construction update:
All blockwork and brick is complete
Hand-…
Read MoreSteel to begin soon at Bloom-Carroll K-5 Elementary
Carroll, Ohio
Bloom-Carroll Local School District’s K-5 Elementary School is moving forward according to schedule. The 108,000 sf school’s four sections (academic and administration wings) now…
Read More