Early Childhood Center at Urban Community School update 5.5.20

May 05, 2020
Cleveland, Ohio  The progress continues at the Early Childhood Education Center on the campus of Urban Community School.  As May begins, the roof membrane is complete, the exterior framing and sheathing is complete, and the interior wall...

Charles Schwab in Westlake update 4.23.20

Apr 23, 2020
Westlake, Ohio  The interior buildout at Charles Schwab in Westlake is now in full swing with complete mep rough-ins, first coat of paint scheduled for next week, and drywall nearing completion. The building’s facade is moving forward...

Safety during COVID-19

Apr 20, 2020
Akron, Ohio Summit Construction has continued operations during the state of Ohio's ongoing battle with COVID-19 as an essential business.  To create and maintain the safest work environment possible, Summit Construction has put...

Lancaster General Sherman Junior High update 4.13.20

Apr 13, 2020
Lancaster, Ohio  Lancaster City School District's 106,000 sf General Sherman Junior High School is forging ahead to completion. Construction update:  All blockwork and brick is complete Hand-rails, aluminum gates and roof ladders are...

Steel to begin soon at Bloom-Carroll K-5 Elementary

Apr 07, 2020
Carroll, Ohio  Bloom-Carroll Local School District’s K-5 Elementary School is moving forward according to schedule.  The 108,000 sf school’s four sections (academic and administration wings) now have CMU bearing walls, MEP rough ins, and...

Crystal Clinic Orthopaedic Center update 04.03.20

Apr 03, 2020
Kent, Ohio The renovation and addition to the existing Crystal Clinic in Kent is moving forward beautifully and on schedule.  The new look of the clinic is more evident each day as the interior continues to progress.  Exterior Brick and...