Madison-Plains Local School District New K-12 School Project 

Project Address: 55 Linson Road 

 

Project Schedule:

Construction Notice to Proceed: August 2026

Substantial Completion: January 2029

 

Bid Timeline: Insert here 

 

Project Description: 

As part of Segment One, partially build one new elementary/middle/high school for the entire PK–5 and 9–12 student population. The overall building square footage is 127,400 sf and breaks down as follows: elementary school = 58,724 sf, middle school = 4,600 sf (common area only) and high school = 64,076 sf. The overall career tech space is 13,583 sf which breaks down as follows: core space = 7,315 sf and program space = 6,268 sf. 

 

Invitation to Bid: 

We invite subcontractors already prequalified by Summit Construction and new vendors in the London and Madison county regions to bid this project. 

 

*Please review our Prequalification Form here. 

 

Trades Needed/ Scopes of Work:

Concrete
Precast Concrete
Masonry
Structural Steel & Metal Fabrications
Cold-Formed Metal Framing, Trusses, and Exterior Sheathing
Rough Carpentry Blocking and Backing 
Waterproofing
Intumescent Fire Protection
Spray Applied Insulation
Expansion Joint Cover Assemblies
Membrane Roofing
Metal Roof System
Caulking
Doors/Frames/Hardware - Material
Doors/Frames/Hardware - Installation
Coiling Counter Doors
Overhead Doors, Sectional and Coiling
Entrances, Storefronts, Glass & Glazing
Safety and Security Films
Metal Framing & Drywall, Ceilings
Resilient Flooring and Carpet
Epoxy Floor Coatings
Hard Tile Floors and Walls
Acoustic Treatments - Panels and Baffles
Painting and Coatings
Visual Display Boards
Directories, Painted Supergraphics, Plaques, Dimensional Letters, Panel Signage, and Post and Panel/Pylon Signage
Fire Extinguishers & Cabinets, Emergency Aid Specialties
Toilet Partitions and Toilet Accessories, Cubicle Curtains & Tracks
Lockers
Wire Mesh Partitions
Wall and Door Protection
Flagpole
Kitchen Equipment
Athletic/Gym Equipment
Kiln and Education Equipment
Playground Equipment
Window Shades
Casework, Countertops, and Solid Surface Shower Enclosure
Telescoping Stands
Greenhouse
Elevator
Fire Protection
Plumbing
Mechanical
HVAC Controls
Electrical & Fire Alarm
Structured Cabling
Audio, Visual, and Sound Systems
Security and Access Controls
Earthwork and Utilities
Tree Clearing
Soil Stabilization
Asphalt Paving, Striping, and Markings
Landscaping and Seeding
Fencing

Architect: Schorr Architects 

 

Renderings:

 

MP Rendering

CMR Project Management Lead: Adam Huwer, Summit Construction

CMR Preconstruction Lead: Scott Montgomery, Summit Construction

 

For additional questions or clarifications about this project, please contact:

Scott Montgomery

Contact

 

Andy Rogers

Contact