News

Crystal Clinic Orthopaedic Center update 04.03.20

SHARE THIS

Kent, Ohio

The renovation and addition to the existing Crystal Clinic in Kent is moving forward beautifully and on schedule.  The new look of the clinic is more evident each day as the interior continues to progress. 

Exterior

  • Brick and split face block are in progress on the north elevation
  • Site grading on the north side is in progress
  • Concrete walkways will follow

Interior

  • Drywall is complete
  • Paint is complete in all units, final coats on corridors are ongoing
  • Casework base and upper cabinets have been installed and countertops will begin shortly
  • Ceiling grid is complete
  • Ceiling tile is in progress
  • Light fixtures and devices are in progress
  • Sprinkler drops are complete
  • HVAC diffusers/exhaust fans and grilles are almost complete
  • Plumbing fixtures have begun
  • Flooring is set to begin in mid April 

Follow along with Crystal Clinic’s progress by following Summit on Instagram and LinkedIn