Construction kicked off in the fall of 2024 for the Pickaway-Ross Construction Trades Lab Addition and Renovation.

The project includes an 18,000 SF addition and renovations to two buildings on campus that will benefit the career center’s Commercial Carpentry and Construction Technologies Programs.

Image removed.addition meeting existing building

lab space

“The new expansion will allow the renovation of lab spaces for Robotics and Manufacturing (RAMTEC), Veterinary Assisting, and Electrical programs, as well as an open lab space for future programming.” (pickawayross.com)

inside trades lab

Renovation

Renovation

Renovations to the main building will upgrade the reception and administration areas, the teacher’s lounge, restrooms, and three program classrooms. A new health clinic will also be added.

The north building renovation will convert the school’s existing RAMTEC space into a Veterinary Lab with an exam room, surgery room, lab, grooming space, kennels, an outdoor canopy with turf, and a washing space for animals.

Reception area

Update from the Project Team: 

Commercial Carpentry & Construction Technologies Addition

  • Light installation is ongoing
  • Storefronts are being constructed
  • Brick installation and painting is ongoing 

Vet Tech Renovation Area

  • Underground plumbing is in progress
  • Canopy foundations and concrete curbs are ongoing 

Administration and Health Clinic Renovation Area

  • Underground plumbing is in progress
  • Framing as well as in-wall MEP’s is ongoing

Teacher’s Lounge and Restroom Renovation Area

  • Framing and in-wall MEP’s are in progress

drone view

drone view

Summit Construction is honored to be serving as CMR for this exciting and impactful career tech project alongside Schorr Architects. 